SR 12 Jameson Canyon - Phase 1

Description: In Napa and Solano County, from Highway 29 to Interstate 80 - Widen from 2 lane highway to 4 lane expressway TCRP#157

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Solano, Napa
City
Zip Code 94503, 94534, 94558
 
Senate District
02
Assembly District 07
Congressional District 01
 
Caltrans District
04
 
 
County/State Route Solano 12
Postmile Begin/End 0 R  2.4
 
County/State Route Napa 12
Postmile Begin/End 0.2 3.3
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  3019      
Lane Miles Added (Mixed)  6      
Peak Period Time Savings (minutes)  247558      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Doanh Nguyen (510) 286-6293   doanh_nguyen@dot.ca.gov
Design (PS&E) Phase
Solano Transportation Authority Janet Adams (707) 424-6010   jadams@sta-snci.com
Right of Way Phase
Caltrans Doanh Nguyen (510) 286-6293   doanh_nguyen@dot.ca.gov
Construction Phase
Caltrans Doanh Nguyen (510) 286-6293   doanh_nguyen@dot.ca.gov
 
Corridor System Management Plan
Caltrans Juliana Gum (510) 286-4579   juliana_gum@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $9,000 $9,000
IIP Augmentation
$0 $5,100 $5,100
CMIA
$73,990 $-19,123 $54,867
Non-bond Funding
State/Federal*
$56,610 $-13,756 $42,854
Local**
$8,900 $-641 $8,259
Non Budgeted ETC
$0 $0 $0
 
Total**** $139,500 $-19,420 $120,080

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$6,900 $400 $7,300 $7,817
Design(PS&E)
$7,700 $1,400 $9,100 $12,796
Right of Way
$19,200 $-3,441 $15,759 $18,825
Construction
$105,700 $-17,779 $87,921 $92,721
 
Total* $139,500 $-19,420 $120,080 $132,159

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
04/01/2001 

01/31/2008 
100  04/01/2001 

01/31/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

 
 

 
 

 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
 

 


Corridor System Management Plan
Adoption Date     09/01/2010  100  12/01/2010  -3 
Implementation Date     09/01/2010  01/01/2011  -4 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 3019
Lane Miles Added (Mixed) 6
Peak Period Time Savings (minutes) 247558

Bond Funding Cost
Adopted:
$73,990,000
Current Approved:
$68,967,000
Actual Expenditures:
$67,794,000

 

Status as of December 31, 2023.